STAGES OF CONSTRUCTION OF THE PYRAMID COMPLEX NEAR TOMSK CITY IN SIBERIA

PHASE 3

The third construction phase of the central pyramid began with the manufacture of the formwork for the upper part of the pyramid shaped resonator chambers of the first level and the mounting of the metal formwork for the pour of the upper half (second part) of the first level of the pyramid.
Placing and strapping of the reinforcement for the upper half (second part) of the first level of the pyramid.
Simultaneously, the formwork frames for the first-level resonator chambers were reinforced to prevent them from being deformed by the pressure of the concrete pour.
Placement of the last formwork elements after which the pour began.
From left to right in the picture:
Vladislav Levchugov (investor of the project) Tomsk,
Andrey Korman (Crimean Center for Human Development),
Valery Uvarov (Researcher, paleo technologist, ideologist and architect of the project), St. Petersburg,
Dmitry Makarov (head of the architectural and construction company OOO "GradoStroyProekt", Moscow).
Details about the ideas and principles embodied in the world's first pyramid complex in Tomsk can be found in the book "Pyramids. Legacy of the gods" by Valery Uvarov.
Contact us
If you have any questions do not hesitate to ask, filling in the form below.
+7 901 301 81 07
+7 964 333 29 36
St.Petersburg, Moscowsky pr. 78-2
All rights to the content of this site belong to
Valery M. Uvarov

The use of this content or part of the content from this site in any way
other than personal acquaintance is possible only with the written
permission of Valery M. Uvarov
All rights reserved
© 2017 All content on this site is protected under copyright